LEVELOG · CONSTRUCTION PROGRESS REPORT

Harbor Row Tower

Harbor Row, Brooklyn, NY (demo job) · Demo General Contractor

Nov 9–15, 2026

Weekly · prepared Nov 16, 2026

High riskSet by the highest risk in this report. Not a judgment of schedule, cost or quality.

  • 4 / 4Working days with site activity
  • 29.8Average workers on site per day▼ 2.6 vs previous (32.4)
  • 34Peak workforce · Nov 13
  • 6Subcontractors on site

First risk in this report HIGH 2 DOB/DOT violations or complaints open: DOB complaint DEMO-C-4471 and DOB violation DEMO-ECB-0398.R1R2

Overview

The badge beside the dates is set by the highest risk in this report. It is not a judgment of schedule, cost or quality.

6 subcontractors worked on site on 4 of 4 working days, averaging 29.8 workers a day with a peak of 34 on Fri Nov 13. That is in line with the previous period (32.4 a day).

Reported work — Kestrel Concrete: formwork on Top deck; Brightway Electric: conduit on floor 13; Northline Mechanical: return ductwork on floors 14–15; Clearspan Glazing: curtain wall panels on floor 10.

Regulatory — 2 DOB/DOT violations or complaints open and 1 record issued in the period.

Schedule — per the project schedule dated Nov 13, 2026: 22 of 40 scheduled activities complete and forecast finish Sep 13, 2027 against an original Sep 6, 2027.

Progress — concrete in progress; electrical rough-in appears complete on floors 1–7 and 9–12, in progress on floor 13; HVAC / ductwork rough-in appears complete on floors 1–14, in progress on floor 15; windows appears complete on floors 1–6 and 8–10 (and 1 more kind of work on the progress page), as read from the daily logs.

Workers on site

Workers on site, per working daySame position in the previous period

See this in the PDF

Changes, risks and what is coming up

Changes since the previous period
  • 1 new DOB/DOT record issued: DOB complaint DEMO-C-4471.R1
  • 1 violation resolved: DOB violation DEMO-ECB-0355.R3
Risks and watch items
  • HIGH 2 DOB/DOT violations or complaints open: DOB complaint DEMO-C-4471 and DOB violation DEMO-ECB-0398.R1R2
  • WATCH Permit expiring within 30 days: DOB permit B00DEMO05-S1 (Nov 24, 2026).R4
Coming up (next 30 days)
  • Tue Nov 24 — DOB permit B00DEMO05-S1 expiresR
  • Thu Dec 3 — Milestone: Superstructure to floor 20S
  • Fri Dec 4 — Milestone: Permanent powerS
Progress (estimated) L

Electrical rough-in — about 55%

HVAC / ductwork rough-in — about 65%

Windows — about 45%

Sprinklers rough-in — about 60%

Estimated from the filed daily logs; see the progress page.

Schedule S

22 of 40 activities complete (count, not a percent)
Finish Sep 13, 2027 vs original Sep 6, 2027 (+7 days)

Per schedule data date Nov 13, 2026

See this in the PDF

Progress by trade and floor (estimated)L

An estimate, read from the lines of the filed daily logs. With a confirmed schedule it is counted over the floors that file names; the count behind each percent is printed beside it. The demo logs carry no photographs, so this sample has no photo page.

How far each kind of work has got on each floor, read from the filed daily logs up to Nov 15, 2026. Week by week: the estimate at the end of each of the last 12 weeks, read from the logs filed up to that day.

Concrete Kestrel Concrete

    not tied to a floor In progress at Top deck

    Concrete (Kestrel Concrete): in progress at Top deck.

    Electrical rough-in Brightway Electric

    1. Floor 1: Done
    2. Floor 2: Done
    3. Floor 3: Done
    4. Floor 4: Done
    5. Floor 5: Done
    6. Floor 6: Done
    7. Floor 7: Done
    8. Floor 8: Started
    9. Floor 9: Done
    10. Floor 10: Done
    11. Floor 11: Done
    12. Floor 12: Done
    13. Floor 13: Active
    14. Floor 14: not reported
    15. Floor 15: not reported
    16. Floor 16: not reported
    17. Floor 17: not reported
    18. Floor 18: not reported
    19. Floor 19: not reported
    20. Floor 20: not reported
    21. Floor 21: not reported
    22. Floor 22: not reported

    about 55%Week by week

    Electrical rough-in (Brightway Electric): appears complete on floors 1–7 and 9–12; in progress on floor 13; started earlier on floor 8; not yet reported on floors 14–22. 11 of 22 floors appear complete, 2 under way.

    HVAC / ductwork rough-in Northline Mechanical

    1. Floor 1: Done
    2. Floor 2: Done
    3. Floor 3: Done
    4. Floor 4: Done
    5. Floor 5: Done
    6. Floor 6: Done
    7. Floor 7: Done
    8. Floor 8: Done
    9. Floor 9: Done
    10. Floor 10: Done
    11. Floor 11: Done
    12. Floor 12: Done
    13. Floor 13: Done
    14. Floor 14: Done
    15. Floor 15: Active
    16. Floor 16: not reported
    17. Floor 17: not reported
    18. Floor 18: not reported
    19. Floor 19: not reported
    20. Floor 20: not reported
    21. Floor 21: not reported
    22. Floor 22: not reported

    about 65%Week by week

    HVAC / ductwork rough-in (Northline Mechanical): appears complete on floors 1–14; in progress on floor 15; not yet reported on floors 16–22. 14 of 22 floors appear complete, 1 under way.

    Windows Clearspan Glazing

    1. Floor 1: Done
    2. Floor 2: Done
    3. Floor 3: Done
    4. Floor 4: Done
    5. Floor 5: Done
    6. Floor 6: Done
    7. Floor 7: Started
    8. Floor 8: Done
    9. Floor 9: Done
    10. Floor 10: Done
    11. Floor 11: not reported
    12. Floor 12: not reported
    13. Floor 13: not reported
    14. Floor 14: not reported
    15. Floor 15: not reported
    16. Floor 16: not reported
    17. Floor 17: not reported
    18. Floor 18: not reported
    19. Floor 19: not reported
    20. Floor 20: not reported
    21. Floor 21: not reported
    22. Floor 22: not reported

    about 45%Week by week

    Windows (Clearspan Glazing): appears complete on floors 1–6 and 8–10; started earlier on floor 7; not yet reported on floors 11–22. 9 of 22 floors appear complete, 1 under way.

    Sprinklers rough-in Tidewater Fire Protection

    1. Floor 1: Done
    2. Floor 2: Done
    3. Floor 3: Done
    4. Floor 4: Done
    5. Floor 5: Done
    6. Floor 6: Done
    7. Floor 7: Done
    8. Floor 8: Done
    9. Floor 9: Done
    10. Floor 10: Done
    11. Floor 11: Done
    12. Floor 12: Done
    13. Floor 13: Done
    14. Floor 14: Active
    15. Floor 15: not reported
    16. Floor 16: not reported
    17. Floor 17: not reported
    18. Floor 18: not reported
    19. Floor 19: not reported
    20. Floor 20: not reported
    21. Floor 21: not reported
    22. Floor 22: not reported

    about 60%Week by week

    Sprinklers rough-in (Tidewater Fire Protection): appears complete on floors 1–13; in progress on floor 14; not yet reported on floors 15–22. 13 of 22 floors appear complete, 1 under way.

    Done — appears completeActive — worked in the last 7 daysStarted — worked earlierNot reported on that floor

    How the estimate is made. Estimated from the filed daily logs: on each floor, work the log reports as complete, or that the next trade in sequence has followed (and the crew has not returned to in a week), counts as complete; work reported on that floor counts as half done; a floor that no log line names for that work counts as not started. Not measured on site and not taken from a schedule. Counted over 22 floors: the 15 a filed daily log has named and 7 more that the confirmed schedule file names (floors 16–22).

    See this in the PDF

    Crews on site, day by dayGL

    Who worked when, and what they reported, from site check-ins and filed daily logs. A bar is days on site, not measured completion.

    • Brightway Electric ElectricalConduit, electrical rough-in · floor 13

      4 days
    • Clearspan Glazing WindowsCurtain wall panels, window installation · floor 10

      4 days
    • Kestrel Concrete ConcreteFormwork, rebar, formwork secured, no pour

      4 days
    • Northline Mechanical HVACReturn ductwork, supply · floors 14–15

      4 days
    • Summit Hoist Hoist and safetyHoist operation, safety watch

      4 days
    • Tidewater Fire Protection SprinklerBranch lines, sprinkler mains · floor 14

      3 days

    A coloured bar: days on site, in the subcontractor's colour. A weekend between two worked days does not break the bar; a working day with nobody there does.

    See this in the PDF

    Schedule and completionS

    Planned vs actual: when you import and confirm your schedule. The dates are the file’s own. A milestone that is not complete shows its current date; a shift under 7 days is in the milestone table only.

    Per Harbor Row Tower Master Schedule.xlsx, data date Nov 13, 2026, confirmed by Project manager (demo). Completion figures are those the schedule itself reports; Levelog does not estimate completion.

    Milestones
    MilestoneOriginalCurrent, or actual if completeStatus
    Superstructure to floor 20Dec 1, 2026Dec 3, 2026UPCOMING
    Permanent powerNov 6, 2026Dec 4, 2026UPCOMING
    Schedule changes shown in the file
    ActivityOriginalCurrentShift
    Permanent powerNov 6Dec 4+28 d
    Hoist removalMar 10Mar 17+7 d
    Substantial completionSep 6Sep 13+7 d
    Topping outDec 10Dec 17+7 d

    Finish or start dates 7 days or more later than the original; smaller shifts are in the milestone table and the schedule file. Dates as they appear in the schedule file; no cause is inferred.

    Scheduled for this period vs. reported
    Scheduled in the schedule
    • Curtain wall floors 1-8 (Sep 15–Nov 10)
    • Ductwork floors 9-16 (Oct 6–Dec 3)
    • Sprinkler floors 9-16 (Oct 14–Dec 10)
    • Electrical rough-in floors 9-16 (Oct 21–Dec 17)
    • and 3 more scheduled in this period
    Reported in daily logs
    • Kestrel Concrete: Formwork
    • Brightway Electric: Conduit
    • Northline Mechanical: Return ductwork
    • Clearspan Glazing: Curtain wall panels
    • Summit Hoist: Hoist operation
    • Tidewater Fire Protection: Branch lines

    Shown side by side for comparison; the report draws no conclusion from differences in wording.

    By floor (activities named for a floor)
    • Floors 1–9 1 of 1 complete on each
    • Floor 10 2 of 2 complete
    • Floors 11–14 1 of 1 complete on each
    • Floors 15–17 1 of 1 complete on each
    • Floors 18–19 0 of 1 complete on each
    • Floor 20 0 of 2 complete
    • Floors 21–22 0 of 1 complete on each

    See this in the PDF

    Workforce and site activityG

    Workers counted once per day from site check-ins; working days are weekdays, excluding U.S. federal holidays, from the first recorded activity.

    • Kestrel Concrete Concrete

      Days on site 4 (previous 5)Avg workers 11.8 (previous 13.2)Peak 14

    • Brightway Electric Electrical · floor 13

      Days on site 4 (previous 5)Avg workers 4.8 (previous 4.8)Peak 5

    • Northline Mechanical HVAC · floors 14–15

      Days on site 4 (previous 5)Avg workers 4.8 (previous 4.8)Peak 5

    • Clearspan Glazing Windows · floor 10

      Days on site 4 (previous 5)Avg workers 3.8 (previous 3.8)Peak 4

    • Summit Hoist Hoist and safety

      Days on site 4 (previous 5)Avg workers 2 (previous 2)Peak 2

    • Tidewater Fire Protection Sprinkler · floor 14

      Days on site 3 (previous 5)Avg workers 3.7 (previous 3.8)Peak 4

    See this in the PDF

    Regulatory and material risksR

    The report names the city records that are open, new, changed or expiring soon. Open violations and open complaints are counted together. The app’s city screen lists every record on the address.

    DOB/DOT feed checked Nov 16, 2026.

    RecordNumberIssuedStatus at period end
    DOB complaintDEMO-C-4471Nov 12, 2026OPEN R1
    DOB violationDEMO-ECB-0398Oct 20, 2026OPEN R2
    DOB violationDEMO-ECB-0355Sep 2, 2026CLOSED — was ACTIVE, changed Nov 9, 2026R3
    DOB permitB00DEMO05-S1Nov 24, 2025ISSUED — expires Nov 24, 2026R4
    DOT permitDEMO-DOT-2201Sep 14, 2026ISSUED — expires Jan 14, 2027R5

    Listed: records open at the end of the period, records issued or changed during it, and permits that expire within 60 days of its end. A permit in force that expires later is not listed.

    Daily site inspections L

    15 inspection items were walked on 3 days; 15 passed, 0 failed. None failed.

    See this in the PDF

    Basis, data notes and evidence

    A source tag anywhere in this sample opens its line of this index. It is the report’s own index: in the product a city record links to the city’s site, and a log is cited by date and id, not linked.

    How to read the progress in this report. Documented — work the subs reported in daily logs. Estimated — the stages and percentages on the progress page, read from those logs by the fixed rules printed there. Measurable — counts or a percent exactly as a confirmed schedule file states them. Verified physical progress — not claimed: nothing here is independently verified on site, and no figure is calculated from headcount.

    What this report does not contain
    • Progress stages and estimates are read from the filed daily logs by the fixed rules on the progress page. They are not measured or independently verified on site, and no figure is derived from headcount.
    • Photographs are supplied in the filed daily logs; their location and date are as filed and are not independently verified.
    • Internal GC coordination (messages, reminders, punch-list assignments, free-text site observations) and individual worker information are not included in this report.
    Data notes
    • Daily logs were filed for 3 of the 4 days with site activity (no filed log on Nov 13).
    • Working days exclude Veterans Day (Nov 11).
    Evidence index
    • GSite check-ins119 check-in records, Nov 9–15 (NFC / QR gate; one worker counts once a day)
    • LFiled daily logs3 daily jobsite logs filed in the periodNov 9 (91f974), Nov 10 (7e5d22), Nov 12 (836c4e)
    • R1DOB complaint DEMO-C-4471DOB record; status ACTIVE a810-bisweb.nyc.gov
    • R2DOB violation DEMO-ECB-0398DOB record; status ACTIVE a810-bisweb.nyc.gov
    • R3DOB violation DEMO-ECB-0355DOB record; status RESOLVED a810-bisweb.nyc.gov
    • R4DOB permit B00DEMO05-S1DOB record; status ISSUED a810-bisweb.nyc.gov
    • R5DOT permit DEMO-DOT-2201DOT record; status ISSUED
    • SProject scheduleHarbor Row Tower Master Schedule.xlsx, data date Nov 13, 2026, confirmed by Project manager (demo)

    site check-ins ·filed daily logs ·DOB/DOT record ·project schedule

    Generated November 16, 2026 8:00 AM ET · engine 2026.11.2 · reference 0889ac53e6 · report demo-wee. The facts printed here are stored with the report.

    See this in the PDF

    Sample report. Words and numbers are the report engine’s output on demo data, laid out here for the web. The product sends it as a PDF.