LEVELOG · CONSTRUCTION PROGRESS REPORT

Harbor Row Tower

Harbor Row, Brooklyn, NY (demo job) · Demo General Contractor

Oct 1–31, 2026

Monthly · prepared Nov 1, 2026

High riskSet by the highest risk in this report. Not a judgment of schedule, cost or quality.

  • 21 / 21Working days with site activity
  • 32.1Average workers on site per day▼ 0.4 vs previous (32.5)
  • 34Peak workforce · Oct 1
  • 6Subcontractors on site

First risk in this report HIGH 2 DOB/DOT violations or complaints open: DOB violation DEMO-ECB-0398 and DOB violation DEMO-ECB-0355.R1R2

Overview

The badge beside the dates is set by the highest risk in this report. It is not a judgment of schedule, cost or quality.

6 subcontractors worked on site on 21 of 21 working days, averaging 32.1 workers a day with a peak of 34 on Thu Oct 1. That is in line with the previous period (32.5 a day).

Reported work — Kestrel Concrete: formwork on Top deck; Brightway Electric: conduit on floors 8–12; Northline Mechanical: return ductwork on floors 9–13; Tidewater Fire Protection: branch lines on floors 8–12.

Regulatory — 2 DOB/DOT violations or complaints open and 1 record issued in the period.

Schedule — per the project schedule dated Oct 30, 2026: 19 of 40 scheduled activities complete and forecast finish Sep 13, 2027 against an original Sep 6, 2027.

Progress — concrete in progress; electrical rough-in appears complete on floors 1–7 and 9–11, in progress on floor 12; HVAC / ductwork rough-in appears complete on floors 1–12, in progress on floor 13; sprinklers rough-in appears complete on floors 1–12 (and 1 more kind of work on the progress page), as read from the daily logs.

Workers on site

Workers on site, weekly averageSame position in the previous period

See this in the PDF

Changes, risks and what is coming up

Changes since the previous period
  • 1 new DOB/DOT record issued: DOB violation DEMO-ECB-0398.R1
Risks and watch items
  • HIGH 2 DOB/DOT violations or complaints open: DOB violation DEMO-ECB-0398 and DOB violation DEMO-ECB-0355.R1R2
  • HIGH 4 daily inspection items recorded as failed in the daily logs: Fall protection (Oct 22), Fall protection (Oct 6), Perimeter fence (Oct 30) and 1 more.L
  • WATCH Permit expiring within 30 days: DOB permit B00DEMO05-S1 (Nov 24, 2026).R3
Coming up (next 30 days)
  • Tue Nov 24 — DOB permit B00DEMO05-S1 expiresR
Progress (estimated) L

Electrical rough-in — about 50%

HVAC / ductwork rough-in — about 55%

Sprinklers rough-in — about 55%

Windows — about 35%

Estimated from the filed daily logs; see the progress page.

Schedule S

19 of 40 activities complete (count, not a percent)
Finish Sep 13, 2027 vs original Sep 6, 2027 (+7 days)

Per schedule data date Oct 30, 2026

See this in the PDF

Progress by trade and floor (estimated)L

An estimate, read from the lines of the filed daily logs. With a confirmed schedule it is counted over the floors that file names; the count behind each percent is printed beside it. The demo logs carry no photographs, so this sample has no photo page.

How far each kind of work has got on each floor, read from the filed daily logs up to Oct 31, 2026. Week by week: the estimate at the end of each of the last 12 weeks, read from the logs filed up to that day.

Concrete Kestrel Concrete

    not tied to a floor In progress at Top deck

    Concrete (Kestrel Concrete): in progress at Top deck.

    Electrical rough-in Brightway Electric

    1. Floor 1: Done
    2. Floor 2: Done
    3. Floor 3: Done
    4. Floor 4: Done
    5. Floor 5: Done
    6. Floor 6: Done
    7. Floor 7: Done
    8. Floor 8: Started
    9. Floor 9: Done
    10. Floor 10: Done
    11. Floor 11: Done
    12. Floor 12: Active
    13. Floor 13: not reported
    14. Floor 14: not reported
    15. Floor 15: not reported
    16. Floor 16: not reported
    17. Floor 17: not reported
    18. Floor 18: not reported
    19. Floor 19: not reported
    20. Floor 20: not reported
    21. Floor 21: not reported
    22. Floor 22: not reported

    about 50%Week by week

    Electrical rough-in (Brightway Electric): appears complete on floors 1–7 and 9–11; in progress on floor 12; started earlier on floor 8; not yet reported on floors 13–22. 10 of 22 floors appear complete, 2 under way.

    HVAC / ductwork rough-in Northline Mechanical

    1. Floor 1: Done
    2. Floor 2: Done
    3. Floor 3: Done
    4. Floor 4: Done
    5. Floor 5: Done
    6. Floor 6: Done
    7. Floor 7: Done
    8. Floor 8: Done
    9. Floor 9: Done
    10. Floor 10: Done
    11. Floor 11: Done
    12. Floor 12: Done
    13. Floor 13: Active
    14. Floor 14: not reported
    15. Floor 15: not reported
    16. Floor 16: not reported
    17. Floor 17: not reported
    18. Floor 18: not reported
    19. Floor 19: not reported
    20. Floor 20: not reported
    21. Floor 21: not reported
    22. Floor 22: not reported

    about 55%Week by week

    HVAC / ductwork rough-in (Northline Mechanical): appears complete on floors 1–12; in progress on floor 13; not yet reported on floors 14–22. 12 of 22 floors appear complete, 1 under way.

    Sprinklers rough-in Tidewater Fire Protection

    1. Floor 1: Done
    2. Floor 2: Done
    3. Floor 3: Done
    4. Floor 4: Done
    5. Floor 5: Done
    6. Floor 6: Done
    7. Floor 7: Done
    8. Floor 8: Done
    9. Floor 9: Done
    10. Floor 10: Done
    11. Floor 11: Done
    12. Floor 12: Done
    13. Floor 13: not reported
    14. Floor 14: not reported
    15. Floor 15: not reported
    16. Floor 16: not reported
    17. Floor 17: not reported
    18. Floor 18: not reported
    19. Floor 19: not reported
    20. Floor 20: not reported
    21. Floor 21: not reported
    22. Floor 22: not reported

    about 55%Week by week

    Sprinklers rough-in (Tidewater Fire Protection): appears complete on floors 1–12; not yet reported on floors 13–22. 12 of 22 floors appear complete.

    Windows Clearspan Glazing

    1. Floor 1: Done
    2. Floor 2: Done
    3. Floor 3: Done
    4. Floor 4: Done
    5. Floor 5: Done
    6. Floor 6: Done
    7. Floor 7: Started
    8. Floor 8: Done
    9. Floor 9: Active
    10. Floor 10: not reported
    11. Floor 11: not reported
    12. Floor 12: not reported
    13. Floor 13: not reported
    14. Floor 14: not reported
    15. Floor 15: not reported
    16. Floor 16: not reported
    17. Floor 17: not reported
    18. Floor 18: not reported
    19. Floor 19: not reported
    20. Floor 20: not reported
    21. Floor 21: not reported
    22. Floor 22: not reported

    about 35%Week by week

    Windows (Clearspan Glazing): appears complete on floors 1–6 and 8; in progress on floor 9; started earlier on floor 7; not yet reported on floors 10–22. 7 of 22 floors appear complete, 2 under way.

    Done — appears completeActive — worked in the last 7 daysStarted — worked earlierNot reported on that floor

    How the estimate is made. Estimated from the filed daily logs: on each floor, work the log reports as complete, or that the next trade in sequence has followed (and the crew has not returned to in a week), counts as complete; work reported on that floor counts as half done; a floor that no log line names for that work counts as not started. Not measured on site and not taken from a schedule. Counted over 22 floors: the 13 a filed daily log has named and 9 more that the confirmed schedule file names (floors 14–22).

    See this in the PDF

    Crews on site, day by dayGL

    Who worked when, and what they reported, from site check-ins and filed daily logs. A bar is days on site, not measured completion.

    • Brightway Electric ElectricalConduit, electrical rough-in · floors 8–12

      21 days
    • Kestrel Concrete ConcreteFormwork, rebar, concrete pour, core walls

      21 days
    • Northline Mechanical HVACReturn ductwork, supply · floors 9–13

      21 days
    • Summit Hoist Hoist and safetyHoist operation, safety watch

      21 days
    • Tidewater Fire Protection SprinklerBranch lines, sprinkler mains · floors 8–12

      21 days
    • Clearspan Glazing WindowsCurtain wall panels, window installation · floors 5–9

      20 days

    A coloured bar: days on site, in the subcontractor's colour. A weekend between two worked days does not break the bar; a working day with nobody there does.

    See this in the PDF

    Schedule and completionS

    Planned vs actual: when you import and confirm your schedule. The dates are the file’s own. A milestone that is not complete shows its current date; a shift under 7 days is in the milestone table only.

    Per Harbor Row Tower Master Schedule.xlsx, data date Oct 30, 2026, confirmed by Project manager (demo). Completion figures are those the schedule itself reports; Levelog does not estimate completion.

    Schedule changes shown in the file
    ActivityOriginalCurrentShift
    Permanent powerNov 6Dec 4+28 d
    Hoist removalMar 10Mar 17+7 d
    Substantial completionSep 6Sep 13+7 d
    Topping outDec 10Dec 17+7 d

    Finish or start dates 7 days or more later than the original; smaller shifts are in the milestone table and the schedule file. Dates as they appear in the schedule file; no cause is inferred.

    Scheduled for this period vs. reported
    Scheduled in the schedule
    • Ductwork floors 1-8 (Aug 10–Oct 5)
    • Sprinkler floors 1-8 (Aug 17–Oct 13)
    • Electrical rough-in floors 1-8 (Aug 24–Oct 20)
    • Curtain wall floors 1-8 (Sep 15–Nov 10)
    • and 8 more scheduled in this period
    Reported in daily logs
    • Kestrel Concrete: Formwork
    • Brightway Electric: Conduit
    • Northline Mechanical: Return ductwork
    • Tidewater Fire Protection: Branch lines
    • Summit Hoist: Hoist operation
    • Clearspan Glazing: Curtain wall panels

    Shown side by side for comparison; the report draws no conclusion from differences in wording.

    By floor (activities named for a floor)
    • Floors 1–9 1 of 1 complete on each
    • Floor 10 2 of 2 complete
    • Floors 11–14 1 of 1 complete on each
    • Floor 15 1 of 1 complete
    • Floors 16–19 0 of 1 complete on each
    • Floor 20 0 of 2 complete
    • Floors 21–22 0 of 1 complete on each

    See this in the PDF

    Workforce and site activityG

    Workers counted once per day from site check-ins; working days are weekdays, excluding U.S. federal holidays, from the first recorded activity.

    • Kestrel Concrete Concrete

      Days on site 21 (previous 22)Avg workers 13.1 (previous 13.4)Peak 14

    • Brightway Electric Electrical · floors 8–12

      Days on site 21 (previous 22)Avg workers 4.8 (previous 4.8)Peak 5

    • Northline Mechanical HVAC · floors 9–13

      Days on site 21 (previous 22)Avg workers 4.8 (previous 4.8)Peak 5

    • Tidewater Fire Protection Sprinkler · floors 8–12

      Days on site 21 (previous 22)Avg workers 3.8 (previous 3.8)Peak 4

    • Summit Hoist Hoist and safety

      Days on site 21 (previous 22)Avg workers 2 (previous 2)Peak 2

    • Clearspan Glazing Windows · floors 5–9

      Days on site 20 (previous 21)Avg workers 3.8 (previous 3.8)Peak 4

    See this in the PDF

    Regulatory and material risksR

    The report names the city records that are open, new, changed or expiring soon. Open violations and open complaints are counted together. The app’s city screen lists every record on the address.

    DOB/DOT feed checked Nov 1, 2026.

    RecordNumberIssuedStatus at period end
    DOB violationDEMO-ECB-0398Oct 20, 2026OPEN R1
    DOB violationDEMO-ECB-0355Sep 2, 2026OPEN R2
    DOB permitB00DEMO05-S1Nov 24, 2025ISSUED — expires Nov 24, 2026R3

    Listed: records open at the end of the period, records issued or changed during it, and permits that expire within 60 days of its end. A permit in force that expires later is not listed.

    Daily site inspections L

    100 inspection items were walked on 20 days; 96 passed, 4 failed. Failed: Perimeter fence (Oct 30), Fall protection (Oct 22), Perimeter fence (Oct 6), Fall protection (Oct 6).

    See this in the PDF

    Basis, data notes and evidence

    A source tag anywhere in this sample opens its line of this index. It is the report’s own index: in the product a city record links to the city’s site, and a log is cited by date and id, not linked.

    How to read the progress in this report. Documented — work the subs reported in daily logs. Estimated — the stages and percentages on the progress page, read from those logs by the fixed rules printed there. Measurable — counts or a percent exactly as a confirmed schedule file states them. Verified physical progress — not claimed: nothing here is independently verified on site, and no figure is calculated from headcount.

    What this report does not contain
    • Progress stages and estimates are read from the filed daily logs by the fixed rules on the progress page. They are not measured or independently verified on site, and no figure is derived from headcount.
    • Photographs are supplied in the filed daily logs; their location and date are as filed and are not independently verified.
    • Internal GC coordination (messages, reminders, punch-list assignments, free-text site observations) and individual worker information are not included in this report.
    Data notes
    • Daily logs were filed for 20 of the 21 days with site activity (no filed log on Oct 7).
    • Working days exclude Columbus Day (Oct 12).
    Evidence index
    • GSite check-ins675 check-in records, Oct 1–31 (NFC / QR gate; one worker counts once a day)
    • LFiled daily logs20 daily jobsite logs filed in the periodOct 1 (ba8380), Oct 2 (296bdd), Oct 5 (a91f32), Oct 6 (624cbd), Oct 8 (4834bb), Oct 9 (4ba380), Oct 13 (74123b), Oct 14 (58eba1), Oct 15 (660cf6), Oct 16 (74b3b1), Oct 19 (357dab), Oct 20 (29e3e0), Oct 21 (66237b), Oct 22 (e88ef3), Oct 23 (2df581), Oct 26 (05d9da), Oct 27 (1931fe), Oct 28 (c7eb14), Oct 29 (0bc046), Oct 30 (ff0a29)
    • R1DOB violation DEMO-ECB-0398DOB record; status ACTIVE a810-bisweb.nyc.gov
    • R2DOB violation DEMO-ECB-0355DOB record; status ACTIVE a810-bisweb.nyc.gov
    • R3DOB permit B00DEMO05-S1DOB record; status ISSUED a810-bisweb.nyc.gov
    • SProject scheduleHarbor Row Tower Master Schedule.xlsx, data date Oct 30, 2026, confirmed by Project manager (demo)

    site check-ins ·filed daily logs ·DOB/DOT record ·project schedule

    Generated November 1, 2026 8:00 AM ET · engine 2026.11.2 · reference e7ee45d77f · report demo-mon. The facts printed here are stored with the report.