LEVELOG · CONSTRUCTION PROGRESS REPORT
Harbor Row Tower
Harbor Row, Brooklyn, NY (demo job) · Demo General Contractor
Oct 26 – Nov 8, 2026
High riskSet by the highest risk in this report. Not a judgment of schedule, cost or quality.
- 10 / 10Working days with site activity
- 31.8Average workers on site per day▼ 0.8 vs previous (32.6)
- 34Peak workforce · Oct 28
- 6Subcontractors on site
First risk in this report HIGH 2 DOB/DOT violations or complaints open: DOB violation DEMO-ECB-0398 and DOB violation DEMO-ECB-0355.
Overview
The badge beside the dates is set by the highest risk in this report. It is not a judgment of schedule, cost or quality.
6 subcontractors worked on site on 10 of 10 working days, averaging 31.8 workers a day with a peak of 34 on Wed Oct 28. That is in line with the previous period (32.6 a day).
Reported work — Kestrel Concrete: formwork on Top deck; Brightway Electric: conduit on floors 11–13; Northline Mechanical: return ductwork on floors 12–14; Clearspan Glazing: curtain wall panels on floors 8–10.
Regulatory — 2 DOB/DOT violations or complaints open.
Schedule — per the project schedule dated Nov 6, 2026: 20 of 40 scheduled activities complete and forecast finish Sep 13, 2027 against an original Sep 6, 2027.
Progress — concrete in progress; electrical rough-in appears complete on floors 1–7 and 9–12, in progress on floor 13; HVAC / ductwork rough-in appears complete on floors 1–13, in progress on floor 14; sprinklers rough-in appears complete on floors 1–13 (and 1 more kind of work on the progress page), as read from the daily logs.
Workers on site
Workers on site, per working daySame position in the previous period
Changes, risks and what is coming up
Changes since the previous period
No material change from the previous period.
Risks and watch items
- HIGH 2 DOB/DOT violations or complaints open: DOB violation DEMO-ECB-0398 and DOB violation DEMO-ECB-0355.
- HIGH 2 daily inspection items recorded as failed in the daily logs: Fall protection (Nov 6) and Perimeter fence (Oct 30).
- WATCH Permit expiring within 30 days: DOB permit B00DEMO05-S1 (Nov 24, 2026).
Coming up (next 30 days)
- Tue Nov 24 — DOB permit B00DEMO05-S1 expires
- Thu Dec 3 — Milestone: Superstructure to floor 20
- Fri Dec 4 — Milestone: Permanent power
Progress (estimated)
Electrical rough-in — about 55%
HVAC / ductwork rough-in — about 60%
Sprinklers rough-in — about 60%
Windows — about 40%
Estimated from the filed daily logs; see the progress page.
Schedule
20 of 40 activities complete (count, not a percent)
Finish Sep 13, 2027 vs original Sep 6, 2027 (+7 days)
Per schedule data date Nov 6, 2026
Progress by trade and floor (estimated)
An estimate, read from the lines of the filed daily logs. With a confirmed schedule it is counted over the floors that file names; the count behind each percent is printed beside it. The demo logs carry no photographs, so this sample has no photo page.
How far each kind of work has got on each floor, read from the filed daily logs up to Nov 8, 2026. Week by week: the estimate at the end of each of the last 12 weeks, read from the logs filed up to that day.
Concrete Kestrel Concrete
not tied to a floor In progress at Top deck
Concrete (Kestrel Concrete): in progress at Top deck.
Electrical rough-in Brightway Electric
- Floor 1: Done
- Floor 2: Done
- Floor 3: Done
- Floor 4: Done
- Floor 5: Done
- Floor 6: Done
- Floor 7: Done
- Floor 8: Started
- Floor 9: Done
- Floor 10: Done
- Floor 11: Done
- Floor 12: Done
- Floor 13: Active
- Floor 14: not reported
- Floor 15: not reported
- Floor 16: not reported
- Floor 17: not reported
- Floor 18: not reported
- Floor 19: not reported
- Floor 20: not reported
- Floor 21: not reported
- Floor 22: not reported
about 55%Week by week
Electrical rough-in (Brightway Electric): appears complete on floors 1–7 and 9–12; in progress on floor 13; started earlier on floor 8; not yet reported on floors 14–22. 11 of 22 floors appear complete, 2 under way.
HVAC / ductwork rough-in Northline Mechanical
- Floor 1: Done
- Floor 2: Done
- Floor 3: Done
- Floor 4: Done
- Floor 5: Done
- Floor 6: Done
- Floor 7: Done
- Floor 8: Done
- Floor 9: Done
- Floor 10: Done
- Floor 11: Done
- Floor 12: Done
- Floor 13: Done
- Floor 14: Active
- Floor 15: not reported
- Floor 16: not reported
- Floor 17: not reported
- Floor 18: not reported
- Floor 19: not reported
- Floor 20: not reported
- Floor 21: not reported
- Floor 22: not reported
about 60%Week by week
HVAC / ductwork rough-in (Northline Mechanical): appears complete on floors 1–13; in progress on floor 14; not yet reported on floors 15–22. 13 of 22 floors appear complete, 1 under way.
Sprinklers rough-in Tidewater Fire Protection
- Floor 1: Done
- Floor 2: Done
- Floor 3: Done
- Floor 4: Done
- Floor 5: Done
- Floor 6: Done
- Floor 7: Done
- Floor 8: Done
- Floor 9: Done
- Floor 10: Done
- Floor 11: Done
- Floor 12: Done
- Floor 13: Done
- Floor 14: not reported
- Floor 15: not reported
- Floor 16: not reported
- Floor 17: not reported
- Floor 18: not reported
- Floor 19: not reported
- Floor 20: not reported
- Floor 21: not reported
- Floor 22: not reported
about 60%Week by week
Sprinklers rough-in (Tidewater Fire Protection): appears complete on floors 1–13; not yet reported on floors 14–22. 13 of 22 floors appear complete.
Windows Clearspan Glazing
- Floor 1: Done
- Floor 2: Done
- Floor 3: Done
- Floor 4: Done
- Floor 5: Done
- Floor 6: Done
- Floor 7: Started
- Floor 8: Done
- Floor 9: Done
- Floor 10: Active
- Floor 11: not reported
- Floor 12: not reported
- Floor 13: not reported
- Floor 14: not reported
- Floor 15: not reported
- Floor 16: not reported
- Floor 17: not reported
- Floor 18: not reported
- Floor 19: not reported
- Floor 20: not reported
- Floor 21: not reported
- Floor 22: not reported
about 40%Week by week
Windows (Clearspan Glazing): appears complete on floors 1–6 and 8–9; in progress on floor 10; started earlier on floor 7; not yet reported on floors 11–22. 8 of 22 floors appear complete, 2 under way.
Done — appears completeActive — worked in the last 7 daysStarted — worked earlierNot reported on that floor
How the estimate is made. Estimated from the filed daily logs: on each floor, work the log reports as complete, or that the next trade in sequence has followed (and the crew has not returned to in a week), counts as complete; work reported on that floor counts as half done; a floor that no log line names for that work counts as not started. Not measured on site and not taken from a schedule. Counted over 22 floors: the 14 a filed daily log has named and 8 more that the confirmed schedule file names (floors 15–22).
Crews on site, day by day
Who worked when, and what they reported, from site check-ins and filed daily logs. A bar is days on site, not measured completion.
Brightway Electric ElectricalConduit, electrical rough-in · floors 11–13
10 daysClearspan Glazing WindowsCurtain wall panels, window installation · floors 8–10
10 daysKestrel Concrete ConcreteFormwork, rebar, concrete pour, core walls
10 daysNorthline Mechanical HVACReturn ductwork, supply · floors 12–14
10 daysSummit Hoist Hoist and safetyHoist operation, safety watch
10 daysTidewater Fire Protection SprinklerBranch lines, sprinkler mains · floors 12–13
10 days
A coloured bar: days on site, in the subcontractor's colour. A weekend between two worked days does not break the bar; a working day with nobody there does.
Schedule and completion
Planned vs actual: when you import and confirm your schedule. The dates are the file’s own. A milestone that is not complete shows its current date; a shift under 7 days is in the milestone table only.
Per Harbor Row Tower Master Schedule.xlsx, data date Nov 6, 2026, confirmed by Project manager (demo). Completion figures are those the schedule itself reports; Levelog does not estimate completion.
Milestones
| Milestone | Original | Current, or actual if complete | Status |
|---|---|---|---|
| Superstructure to floor 20 | Dec 1, 2026 | Dec 3, 2026 | UPCOMING |
| Permanent power | Nov 6, 2026 | Dec 4, 2026 | UPCOMING |
Schedule changes shown in the file
| Activity | Original | Current | Shift |
|---|---|---|---|
| Permanent power | Nov 6 | Dec 4 | +28 d |
| Hoist removal | Mar 10 | Mar 17 | +7 d |
| Substantial completion | Sep 6 | Sep 13 | +7 d |
| Topping out | Dec 10 | Dec 17 | +7 d |
Finish or start dates 7 days or more later than the original; smaller shifts are in the milestone table and the schedule file. Dates as they appear in the schedule file; no cause is inferred.
Scheduled for this period vs. reported
Scheduled in the schedule
- Curtain wall floors 1-8 (Sep 15–Nov 10)
- Ductwork floors 9-16 (Oct 6–Dec 3)
- Sprinkler floors 9-16 (Oct 14–Dec 10)
- Concrete floor 15 (Oct 21–Oct 27)
- and 3 more scheduled in this period
Reported in daily logs
- Kestrel Concrete: Formwork
- Brightway Electric: Conduit
- Northline Mechanical: Return ductwork
- Clearspan Glazing: Curtain wall panels
- Tidewater Fire Protection: Branch lines
- Summit Hoist: Hoist operation
Shown side by side for comparison; the report draws no conclusion from differences in wording.
By floor (activities named for a floor)
- Floors 1–9 1 of 1 complete on each
- Floor 10 2 of 2 complete
- Floors 11–14 1 of 1 complete on each
- Floors 15–16 1 of 1 complete on each
- Floors 17–19 0 of 1 complete on each
- Floor 20 0 of 2 complete
- Floors 21–22 0 of 1 complete on each
Workforce and site activity
Workers counted once per day from site check-ins; working days are weekdays, excluding U.S. federal holidays, from the first recorded activity.
Kestrel Concrete Concrete
Days on site 10 (previous 9)Avg workers 12.6 (previous 13.4)Peak 14
Brightway Electric Electrical · floors 11–13
Days on site 10 (previous 9)Avg workers 4.8 (previous 4.9)Peak 5
Northline Mechanical HVAC · floors 12–14
Days on site 10 (previous 9)Avg workers 4.8 (previous 4.9)Peak 5
Clearspan Glazing Windows · floors 8–10
Days on site 10 (previous 8)Avg workers 3.8 (previous 3.9)Peak 4
Tidewater Fire Protection Sprinkler · floors 12–13
Days on site 10 (previous 9)Avg workers 3.8 (previous 3.9)Peak 4
Summit Hoist Hoist and safety
Days on site 10 (previous 9)Avg workers 2 (previous 2)Peak 2
Regulatory and material risks
The report names the city records that are open, new, changed or expiring soon. Open violations and open complaints are counted together. The app’s city screen lists every record on the address.
DOB/DOT feed checked Nov 9, 2026.
| Record | Number | Issued | Status at period end | |
|---|---|---|---|---|
| DOB violation | DEMO-ECB-0398 | Oct 20, 2026 | OPEN | |
| DOB violation | DEMO-ECB-0355 | Sep 2, 2026 | OPEN | |
| DOB permit | B00DEMO05-S1 | Nov 24, 2025 | ISSUED — expires Nov 24, 2026 |
Listed: records open at the end of the period, records issued or changed during it, and permits that expire within 60 days of its end. A permit in force that expires later is not listed.
Daily site inspections
50 inspection items were walked on 10 days; 48 passed, 2 failed. Failed: Fall protection (Nov 6), Perimeter fence (Oct 30).
Basis, data notes and evidence
A source tag anywhere in this sample opens its line of this index. It is the report’s own index: in the product a city record links to the city’s site, and a log is cited by date and id, not linked.
How to read the progress in this report. Documented — work the subs reported in daily logs. Estimated — the stages and percentages on the progress page, read from those logs by the fixed rules printed there. Measurable — counts or a percent exactly as a confirmed schedule file states them. Verified physical progress — not claimed: nothing here is independently verified on site, and no figure is calculated from headcount.
What this report does not contain
- Progress stages and estimates are read from the filed daily logs by the fixed rules on the progress page. They are not measured or independently verified on site, and no figure is derived from headcount.
- Photographs are supplied in the filed daily logs; their location and date are as filed and are not independently verified.
- Internal GC coordination (messages, reminders, punch-list assignments, free-text site observations) and individual worker information are not included in this report.
Data notes
- Daily logs were filed for 10 of the 10 days with site activity.
Evidence index
- GSite check-ins318 check-in records, Oct 26–Nov 8 (NFC / QR gate; one worker counts once a day)
- LFiled daily logs10 daily jobsite logs filed in the periodOct 26 (05d9da), Oct 27 (1931fe), Oct 28 (c7eb14), Oct 29 (0bc046), Oct 30 (ff0a29), Nov 2 (72f31e), Nov 3 (d27a0d), Nov 4 (d1ed22), Nov 5 (d87add), Nov 6 (f4c452)
- R1DOB violation DEMO-ECB-0398DOB record; status ACTIVE a810-bisweb.nyc.gov
- R2DOB violation DEMO-ECB-0355DOB record; status ACTIVE a810-bisweb.nyc.gov
- R3DOB permit B00DEMO05-S1DOB record; status ISSUED a810-bisweb.nyc.gov
- SProject scheduleHarbor Row Tower Master Schedule.xlsx, data date Nov 6, 2026, confirmed by Project manager (demo)
site check-ins ·filed daily logs ·DOB/DOT record ·project schedule
Generated November 9, 2026 8:00 AM ET · engine 2026.11.2 · reference c7e1b4934d · report demo-biw. The facts printed here are stored with the report.
Sample report. Words and numbers are the report engine’s output on demo data, laid out here for the web. The product sends it as a PDF.